Pipeline prior to installation of repair. This photograph shows the preparations stage when the pipe was sandblasted. |
This photograph shows the significant level of corrosion that existed prior to the repair. |
|

|

|
|
Mixing epoxy putty that is necessary for filling in pits and areas with significant corrosion. |
Priming the pipe after its surface has been properly cleaned. |
|

|

|
|
Laying out the fiberglass cloth prior to saturation. The cloth is cut to length, depending on the geometry of the pipe and severity of corrosion. |
The fiberglass cloth is saturated using the two-part epoxy resin mixture. This process may be streamlined so that one group saturates the cloth, while another installs. |
|

|

|
|
Continued priming of pipe surface. |
Rolling up saturated cloth on applicator. The applicator is a convenient way for transporting the saturated cloth to the pipe and also assists in tensioning during installation. |
|

|

|
|
One team of the installers continues priming the pipe surface. |
Installing saturated cloth on the pipe using the applicator. |
|

|

|
|
Note how even weld-o-lets can be repaired using Armor Plate Pipe Wrap. Cloth is cut to fit geometry any piping configuration or geometry. |
Another job made possible by the Armor Plate, Inc. team! |